BGI.INC - REF - SANDS & STONES FOR CONSTRUCTION [VN]
LAND TRANSPORTATION PROJECT FOR TAN SON NHAT AIRPORT IN HCM
1. Introduction
2. Total amount of soil to be transported [3,000,000 cubic meters]
- Phase 01 - From March 2020 to June 2023 [Completed]
3. Construction time & progress
- Construction time [2.5 years]
- Construction progress [7,000 blocks per day]
4. Construction equipment
- Excavators [0]
- Morning scorpion [0]
- Barges [0]
- Dump truck [54 units]
5. Construction status
- Phase 01 - [complete]
REF - CONTACT TO ORDER SAND & STONE
- Tel - 1900636278 [press 6] - Mobile : Updating
- Email: b.refvn@gmail.com - Website: bleogroups.com
- Address : 561 A, Vin-pearl plaza, Ward 25, Dien Bien Phu Street, Binh Thanh district, Ho Chi Minh city