BGI.INC - REF - SANDS & STONES FOR CONSTRUCTION [VN]


LAND TRANSPORTATION PROJECT FOR TAN SON NHAT AIRPORT IN HCM

1. Introduction

2. Total amount of soil to be transported [3,000,000 cubic meters]

  • Phase 01 - From March 2020 to June 2023 [Completed]

3. Construction time & progress

  • Construction time [2.5 years]
  • Construction progress [7,000 blocks per day]

4. Construction equipment

  • Excavators [0]
  • Morning scorpion [0]
  • Barges [0]
  • Dump truck [54 units]

5. Construction status

  • Phase 01 - [complete]

REF - CONTACT TO ORDER SAND & STONE

  • Tel - 1900636278 [press 6] - Mobile : Updating
  • Email: b.refvn@gmail.com - Website: bleogroups.com
  • Address : 561 A, Vin-pearl plaza, Ward 25, Dien Bien Phu Street, Binh Thanh district, Ho Chi Minh city